Saltar al contenido
Production & development
  • Repsol produces about 30,000 barrels of oil equivalents per day from fields in the Norwegian shelf. It is operator for the Gyda, Blane, Yme and Rev fields and has ownership interests in several others.

    In Norway, Repsol operates the Blane, Gyda, Rev and Yme fields. We also hold interests in a number of non-operated fields with associated production facilities and intrafield pipelines including Gudrun, Brage, Veslefrikk, Visund, Mikkel, Huldra and Tambar East.

Gyda

Gyda

The Gyda field was proven in 1980 and developed by the use of an integrated steel platform at a depth of 66 meters. The oil was transported by pipeline to Teesside via Ekofisk. The gas was piped to the Ekofisk complex and on to Emden. 

In June 2017 the Norwegian authorities approved the decommission plan for the Gyda field. The decommission scope includes permanent plugging of 32 wells on the field, removal of platform and undercarriage, as well as removal of installations on the seabed. All Gyda installations should be removed by 2023.

Operator:

  • Repsol Norge AS

Production start-up:

  • 21 june 1990

Cease of Production:

  • 29 february 2020

Licensees:

  • Repsol Norge AS 61% 
  • INEOS E&P Norge AS 34% 
  • KUFPEC Norway AS 5%

Yme

Yme

The Yme field was discovered in 1987 located in Block 9/2 and 9/5 in the Egersund Basin, approximately 100 km from the Norwegian coastline. The field was in production from 1996 to 2001. The main reason for abandonment was the combination of high cost and low oil prices. Current licensees were awarded the rights to block 9/2 and 9/5 (production license 316/316B) 18 June 2004. 

A Plan for Development and Operation (PDO) for Yme re-development was approved by the Norwegian Government 11 May 2007. This re-development was based on a lease of a production unit (MOPU platform) that was installed summer 2011. Due to the discovery of significant structural defects on the MOPU it was removed from the field August 2016 and handed over to the platform-owner. 

On 19 December 2017 Repsol submitted a revised Plan for Development and Operation (PDO) of the Yme field to the Norwegian Ministry of Petroleum and Energy. On 23 March 2018 the revised plan was approved by the Ministry.

The Yme New Development Project consists of the engineering, procurement, construction and installation of a new wellhead module on top of existing facilities at the Yme field, the modifications and upgrading of the Maersk Inspirer Mobile Offshore Drilling and Production Unit prior to installation in the field and subsequent hook-up to existing wells in and installations on the seabed offshore. Mærsk Inspirer has previously been used for drilling and production at the Volve field.

From autumn 2018 until 29th of December 2020 the Mærsk Inspirer was at the Aker Solution’s yard in Egersund for upgrading and modifications work at the yard.

The Mærsk Inspirer left the Aker Solution’s yard in Egersund on the 29th of December 2020 and was successfully installed at the Yme field in the Southern North Sea on the 31st of December 2020.

With the installation of the Mærsk Inspirer in the Yme field, the project will now enter the offshore hook-up and commissioning phase. Planned first oil from the Yme field is 2H 2021.


Licensees:

  • Repsol Norge AS (55% working interest) 
  • Lotos Exploration and Production Norge AS (20% working interest) 
  • KUFPEC Norway AS (10% working interest) 
  • OKEA AS (15% working interest)
 


Documents (Information only available in Norwegian)

Utbygging og drift av Yme: 
 
Avslutning av Yme-feltet: 
- høringsbrev 2015 her PDF (2,03 MB)
- forslag til utredningsprogram 2015 her PDF
- konsekvensutredning 2016 her
 
Yme New Development: 
- høringsbrev utredningsprogram 2016 her
- forslag til utredningsprogram 2016 her
- høringsbrev for tillegg til konsekvensutredning 2017 her
- tillegg til konsekvensutredning 2017 her

- Repsol Norges tilsvar til høringsuttalelser til tillegg til konsekvensutredning 2017 her PDF (124 KB)

- Yme New Development- kraft fra land rapport her PDF (1,4 MB)

- "Yme New Development- high level evaluation of electrification alternative” rapport her PDF (2,3 MB)

Blane

Blane is developed with a subsea facility, which is tied back to the Ula field. The subsea installation is situated on the British Continental Shelf. The ocean depth at the site is around 70 meters.

Operator:

  • Repsol Norge AS

Licensees in Blane Unit:

  • Repsol Norge AS: 18% 
  • Talisman Sinopec Energy UK: 25% 
  • Rock Oil: 12,5% 
  • Dana Petroleum:12,5% 
  • JX Nippon Oil: 14% 
  • Faraoe Petroleum: 18%

Rev

Rev was discovered in February 2001 and commenced production in January 2009. The three wells are situated on the NCS and a buried production pipeline carries the gas and condensate to the Armada platform on the UKCS for processing.

Operator:

  • Repsol Norge AS

Production start-up:

  • 2009

Licensees:

  • Repsol Norge AS70% 
  • Petoro AS 30%

On 16th April 2018 the Rev UKCS decommissioning programme was approved by the Secretary of State. A Copy of this document along with the EIA and Comparative assessment can be found below and also on OPRED website, see link below:

https://www.gov.uk/guidance/oil-and-gas-decommissioning-of-offshore-installations-and-pipelines#table-of-approved-decommissioning-programmes

Brage

Brage is developed with a platform resting on the seabed, encompassing drilling, treatment and accommodation facilities on a steel jacket. The area’s ocean depth is 140 meters. Originally, the Brage field was supposed to be shut down in 2005. The fields license periode expires in 2015. A license extension to 2030 is now under consideration by the authorities. 1 October 2013, Wintershall took over Equinorl's share in the field and become the operator.

Operator:

  • Wintershall Norge ASA

Production start-up:

  • September 1993

Licensees:

  • Repsol Norge AS 33.8% 
  • Wintershall Norge ASA 35.2% 
  • Vår Energi AS: 12.3 %
  • DNO Norge AS: 14.3%
  • Neptune Energy Norge AS: 4.4 %

Gudrun

Gudrun Photo courtesy of Equinor

Gudrun is developed with a traditional steel platform resting on the seabed. The platform have capacity for partial treatment of oil and gas, before the hydrocarbons are sent via pipeline to Sleipner.

Oil and gas is transported from the Gudrun field to the Sleipner A platform. The gas is transported onward to the gas markets from Sleipner A. The oil is routed together with the Sleipner condensate to Kårstø for shipping.

Gudrun was first proven in 1975.

Licensees:

  • Repsol Norge AS 15%
  • Equinor Energy AS (op) 36%
  • Neptune Energy Norge AS 25%
  • OMV (Norge) AS 24%

Visund

Visund is an oil and gas field in blocks 34/8 and 34/7, 22 kilometres north-east of the Gullfaks field in the Tampen area of the Norwegian North Sea.

It came on stream in the spring of 1999, this development embraces a floating production, drilling and quarters platform.

The subsea-completed wells on the field are tied back to the floater with flexible risers. Oil is piped to Gullfaks for storage and export. The Visund field began producing gas and exporting it to continental Europe on 7 October 2005.

Licensees:

  • Repsol Norge AS 7,7%
  • Equinor Energy AS (op) 53,2%
  • Petoro AS 30%
  • ConocoPhillips Skandinavia AS 9,1%

Veslefrikk

The Veslefrikk field was proven in 1981 and has been developed with a well-head platform (Veslefrikk A) resting on the seabed, and a semi-subersible platform with a processing facility and accomodation quarters (Veslefrikk B). The ocean depths at the installations are 175 meters.

Operator:

  • Equinor Petroleum AS

Production start-up:

  • 26 december 1989

Licensees:

  • Petoro AS 37% 
  • Repsol Norge AS 27% 
  • Equinor Petroleum AS 18% 
  • RWE Dea Norge AS 13.5% 
  • Wintershall Norge ASA 4.5%

Mikkel

Mikkel lies 35 kilometres south of the Midgard deposit on Equinor’s Åsgard field in the Norwegian Sea. It has been developed with a subsea production facility tied back to the seabed installations on Midgard, which in turn form part of the Åsgard development.

The Mikkel system comprises two subsea templates with a total of three production wells.

The condensate will go in existing flowlines to the Åsgard C storage ship for export, while gas is piped through the Åsgard Transport trunkline to the Kårstø complex north of Stavanger. 

Mikkel has been producing gas and condensate (light oil) since 1 August 2003.

Licensees:

  • Repsol Norge AS 7,65%
  • Vår Energi AS 48,38%
  • Equinor Energy AS (op) 43.97%
Apply now

Apply now

Here you can post your resume and apply for job openings.
Local Contact

Local Contact

Grethe Elise Foldnes

Manager External Affairs 

Telephone: + 47 52 00 18 85 

Mob: + 47 992 30 931 

e-mail: gefoldnes@repsol.com